Auxiliary Dwelling Units
California Auxiliary Dwelling Units.
Auxiliary Dwelling units are a way to increase your income without new asset purchases. You can add, in many areas of the country, a residential unit on your existing lot. Each State, City ETC has unique rules.
Here is
Californias ADU website
.
Here is Californias Auxiliary Unit Handbook (
PDF File
)
Here are the rules for
Cupertino California Auxiliary Dwelling Units
.
Commission a ADU Sculptural Residence, and use it as a unique new dwelling on your lot.
Contact me, let us discuss your project.
Building Process and
Requirements...
The process of building a home is complex and detailed. The following may seem overwhelming, but is included to outline the project and all that is involved.
Below are a few of the general requirements.
A much more detailed list will be created prior to the beginning of your project.
You do not need to know all of this in order to create a Sculpture Home.
The general contractor will take care of all your home building requirements.
- Create the overall Sculpture Design
- Select lot
- Obtain permits
- Prepare site for materials
- Install office trailer
- Review plans and begin build
- Prepare and excavate site
- Basement or Subfloor installation
- Erect frame
- Roofing
- Erect interior wall partitions
- Install pre-cut structural and insulated panels
- Build fireplace and chimney
- Install exterior windows and doors
- Rough plumbing
- Rough HVAC
- Heating
- Ventilation
- Air conditioning
- Rough electrical
- Framing inspection
- Interior walls and ceilings
- Paint and stain
- Finish flooring
- Interior carpentry and trim
- Finish plumbing
- Finish HVAC
- Finish electrical
- Exterior finish and trim
- Inspect work of subcontractors
- Final inspection
- Landscaping
- Create final punch/to do list
- Call for final building inspection
- Obtain occupancy permit
Another more detailed list:
HOUSE CONSTRUCTION SEQUENCE GUIDE
- *COMPLETE ALL TASKS WITH LOWER "DO" NUMBER FIRST.
- *TASKS WITH SAME "DO" NUMBER CAN BE DONE SIMULTANEOUSLY
- *IGNORE TASKS NOT APPLICABLE TO YOUR JOB
- DO TASKS TO BE DONE
- 1 ( ) SELECT LOT
- 1 ( ) GET PERK TEST BEFORE BUYING LOT IS SEPTIC TANK REQUIRED
- 1 ( ) GET A WRITTEN GUARANTEE THAT SEWER IS STUBBED OUT TO LOT IF ON SEWER
- 2 ( ) SELECT PLANS AND SPECIFICATIONS
- 3 ( ) DEVELOP PLOT PLAN
- 4 ( ) ESTIMATE COSTS
- 5 ( ) GET MORTGAGE COMMITMENT
- 6 ( ) GET CONSTRUCTION LOAN
- 7 ( ) BUY BUILDING PERMIT
- 8 ( ) PAY ELECTRICAL DEPOSIT
- 8 ( ) PAY WATER TAP FEE AND DEPOSIT
- 8 ( ) PAY GAS DEPOSIT IF GAS IS TO BE USED
- 8 ( ) ORDER LONG LEAD ITEMS: WINDOWS, DOORS, BRICK, ROOFING, STEEL, FLOOR AND ROOF TRUSSES. (CHECK SUPPLIERS FOR OTHERS)
- 8 ( ) BUY BUILDER'S RISK INSURANCE
- 8 ( ) LOCATE LOT STAKES ---SURVEY IF ANY DOUBTS
- 8 ( ) BATTER BOARD MATERIAL ON SITE
- 8 ( ) LOCATE SEWER STUB-OUT OR SEPTIC SYSTEM LOCATION FOR POSITIVE DRAINAGE
- 9 ( ) SET TEMPORARY ELECTRICAL POWER POLE
- 9 ( ) ORDER TEMPORARY WATER SERVICE
- 9 ( ) SITE PREPARATION: LOCATE HOUSE AND EXCAVATE
- 10 ( ) SET BATTER BOARDS
- 10 ( ) ORDER TEMPORARY ELECTRICAL POWER
-
- **SELECT ONE OF FOLLOWING THREE FOUNDATION OPTIONS
- **MONOLITHIC SLAB OPTION, HOUSE AND GARAGE
- 11 ( ) FORM MATERIAL FOR MONOLITHIC FOOTINGS SLABS, PORCHES AND HEATING UNIT(S) ON SITE
- 11 ( ) EXCAVATE AS NECESSARY FOR FOOTING SLAB, PORCHES, AND HEATING UNIT
- 12 ( ) SET CONCRETE FORMS
- 13 ( ) BACK-FILL AND PACK UNDER SLAB AREA AS REQUIRED
- 14 ( ) SET REINFORCING STEEL FOR FOOTINGS
- 15 ( ) APPLY 4" OF GRAVEL LIMESTONE IN HOUSE AND GARAGE SLAB AREAS
- 16 ( ) SLAB PLUMBING ROUGH-IN
- 17 ( ) UTILITY AND AIR CONDITIONING PIPES, DUCTS AND WIRING UNDER FOOTING AND SLAB AREAS
- 18 ( ) TERMITE TREATMENT
- 18 ( ) SPOT SURVEY, IF ANY DOUBTS OR IF REQQUIRED NOW BY MORTGAGE CO. ---- ELSE, AFTER DECKS AND ALL CONCRETE HAVE BEEN COMPLETED
- 19 ( ) LAY POLYETHYLENE AND WIRE MESH IN HOUSE, GARAGE SLAB AREAS
- 20 ( ) INSPECT FOOTING, HOUSE/SLAB AND GARAGE/SLAB PREPARATION
- 21 ( ) POUR FOOTING (HOUSE SLAB, GARAGE SLAB, PORCHES AND HEATING UNIT PAD(S) CONCRETE)
- 22 ( ) SKIP TO "CONTINUE
-
- **RAISED SLAB OPTION (FOOTING WITH FOUNDATION, HOUSE SLAB AND GARAGE SLAB)
- 11 ( ) FORM MATERIAL FOR FOOTINGS, SLABS, PORCHES AND HEATING UNIT(S) ON SITE
- 12 ( ) EXCAVATE AS REQUIRED
- 13 ( ) DIG FOOTINGS
- 14 ( ) SET CONCRETE FORMS
- 15 ( ) SET REINFORCING STEEL FOR FOOTINGS
- 16 ( ) FOOTING INSPECTION
- 16 ( ) TERMITE TREATMENT
- 16 ( ) SPOT SURVEY (IF ANY DOUBTS OR IF REQUIRED BY MORTGAGE CO. NOW --- ELSE, AFTER DECKS AND ALL CONCRETE HAVE BEEN COMPLETED)
- 16 ( ) CONCRETE BLOCKS, SAND AND MORTAR MIX ON SITE
- 17 ( ) LAY FOUNDATION CONCRETE BLOCKS
- 18 ( ) BACK-FILL AND PACK UNDER SLAB AREAS IF REQUIRED
- 19 ( ) SET ADDITONAL CONCRETE FORMS IF NEEDED
- 20 ( ) APPLY 4" OF GRAVEL/LIMESTONE IN HOUSE AND GARAGE SLAB AREAS
- 21 ( ) SLAB PLUMBING ROUGH-IN
- 22 ( ) UTILITY AND AIR CONDITIONING: PIPES, DUCTS AND WIRING, PERIMETER INSULATION UNDER SLAB AREAS
- 23 ( ) LAY POLYETHYLENE AND WIRE MESH IN HOUSE AND GARAGE SLAB AREAS
- 23 ( ) INSPECT HOUSE SLAB AND GARAGE SLAB PREPARATION
- 24 ( ) POUR HOUSE AND GARAGE PORCHES AND HEATING UNIT(S) CONCRETE
- 25 ( ) SKIP TO "CONTINUE"
-
- **CRAWL SPACE OPTION (HOUSE CRAWL SPACE WITH GARAGE SLAB)
- 11 ( ) DIG FOOTINGS FOR HOUSE, GARAGE AND INTERIOR GIRDER SUPPORT POSTS
- 12 ( ) SET FORMS FOR FOOTINGS
- 13 ( ) SET REINFORCING STEEL FOR FOOTINGS
- 14 ( ) FOOTING INSPECTION
- 14 ( ) TERMITE TREATMENT
- 14 ( ) SPOT SURVEY (IF ANY DOUBTS OR IF NOW REQUIRED BY MORTGAGE CO. ---- ELSE, AFTER DECKS AND ALL CONCRETE HAVE BEEN COMPLETED.)
- 15 ( ) POUR FOOTING CONCRETE
- 15 ( ) CONCRETE BLOCKS, SAND AND MORTAR MIX ON SITE
- 15 ( ) ANCHOR BOLTS AND FOUNDATION VENTS ON SITE
- 16 ( ) LAY FOUNDATION CONCRETE BLOCKS
- 16 ( ) SET FORMS FOR GARAGE, PORCHES AND HEATING UNIT(S)
- 17 ( ) APPLY 4" OF GRAVEL/LIMESTONE IN GARAGE SLAB AREA
- 18 ( ) LAY POLYETHYLENE AND WIRE MESH IN GARAGE SLAB AREA
- 19 ( ) POUR GARAGE, PORCHES, AND HEATING UNIT(S) CONCRETE
- 19 ( ) FRAMING MATERIALS THRU SUB-FLOOR ON SITE
- 20 ( ) INSTALL TERMITE SEALS, SILLS, GIRDERS, FLOOR JOISTS AND/OR TRUSSES, BANDS, BRIDGING, BLOCKING AND SUB-FLOORING
- 21 ( ) SKIP TO "CONTINUE"
-
- 26 ( ) FRAMING MATERIALS ON SITE
- 26 ( ) ONE-PIECE FIBERGLASS BATH UNITS ON SITE
- 26 ( ) PRE-FAB FIREPLACE MATERIALS ON SITE
- 27 ( ) ERECT FRAMING STRUCTURE
- 28 ( ) INSTALL PRE-FAB FIREPLACE
- 28 ( ) PLUMBING: TOP-OUT SLAB, OR ROUGH-IN CRAWL SPACE
- 28 ( ) RUN GAS LINE TO HOUSE, IF GAS IS TO BE USED
- 28 ( ) DECK ROOF AND APPLY ROOF PAPER
- 28 ( ) APPLY EXTERIOR SHEATHING
- 29 ( ) INSPECT PLUMBING
- 29 ( ) HEAT AND AIR DUCTING ROUGH-IN
- 29 ( ) BACK-FILL UTILITY DITCHES AND FOUNDATION (OPTIONAL NOW OR LATER)
- 29 ( ) SHEET METAL: VALLEYS, VENTS ON ROOF, DRYER VENT
- 30 ( ) INSTALL CORNICE
- 30 ( ) INSTALL WINDOWS AND EXTERIOR DOORS
- 30 ( ) PRESSURE PLUMBING ROUGH-IN
- 30 ( ) APPLY ROOFING
- 30 ( ) PAINT CORNICE
- 30 ( ) PAINT WINDOWS AND EXTERIOR DOORS
- 31 ( ) CENTRAL VACUUM ROUGH-IN
- 31 ( ) INSTALL GUTTERS
- 31 ( ) INSTALL FLOOR PARTICAL-BOARD
- 31 ( ) INSTALL WINDOW AND EXTERIOR DOOR HARDWARE
- 32 ( ) OTHER CONCRETE FORMS (BEFORE NEXT CONCRETE POUR)
- 32 ( ) ELECTRICAL ROUGH-IN
- 32 ( ) TELEPHONE ROUGH-IN
- 32 ( ) T.V. LEAD OR CABLE ROUGH-IN
- 32 ( ) THERMOSTAT WIRING
- 32 ( ) INTERCOM ROUGH-IN
- 32 ( ) FRAMING INSPECTION
- 33 ( ) MEASURE FOR CABINETS, VANITIES AND MARBLE TOPS
- 33 ( ) INSTALL INSULATION BATTS AND SPRAY FOAM IN WALLS, FLOOR AND CEILING, WHERE REQUIRED
- 33 ( ) APPLY EXTERIOR SIDING
- 33 ( ) BRICK, SAND AND MORTAR MIX ON SITE
- 33 ( ) BUILD CONVENTIONAL FIREPLACE AND APPLY FLASHING
- 34 ( ) HANG SHEET ROCK AND SPRAY CEILING
- 34 ( ) LAY BRICK
- 34 ( ) DIG WELL, IF REQUIRED
- 34 ( ) INSTALL SEPTIC SYSTEM, IF REQUIRED
- 35 ( ) BUILD DECKS AND EXTERIOR STAIRS
- 35 ( ) BLOW IN ATTIC INSULATION
- 35 ( ) TIE-IN WATER OR WELL AND SEWER OR SEPTIC SYSTEM
- 35 ( ) TIE-IN GAS, IF GAS IS TO BE USED
- 35 ( ) INSTALL DOWNSPOUTS
- 35 ( ) INSTALL SHUTTERS
- 36 ( ) INSTALL CABINETS, VANITIES, AND MARBLE TOPS
- 36 ( ) INSTALL ACCESS DOORS TO CRAWL SPACE, ATTIC AND PLUMBING
- 36 ( ) INSTALL DISAPPEARING STAIRS
- 36 ( ) COMPLETE STAIRWAYS: TREADS, RISERS AND RAILS
- 36 ( ) INSTALL INTERIOR PANELING
- 36 ( ) INSTALL INTERIOR DOORS
- 36 ( ) INSTALL GARAGE DOOR(S)
- 36 ( ) COMPLETE HEAT AND AIR ROUGH-IN
- 36 ( ) INSPECT PLUMBING, WATER AND SEWER TIE-INS
- 37 ( ) STAIN OR PAINT CABINETS, IF REQUIRED
- 37 ( ) INSTALL CERAMIC TILE FLOORS AND WALLS
- 37 ( ) INSTALL GARAGE PANELING
- 37 ( ) SET HEAT AND AIR UNIT(S)
- 38 ( ) INSTALL TRIM MOLDING AND SHELVES
- 38 ( ) PAINT EXTERIOR DUCT-WORK, IF REQUIRED
- 38 ( ) COMPLETE ALL PAINTING
- 39 ( ) HANG WALLPAPER
- 39 ( ) INSTALL APPLIANCES
- 40 ( ) PLUMBING FINAL: INSTALL WATER HEATER(S), DISHWASHER, DISPOSAL, AND ALL FIXTURES EXCEPT COMMODES
- 40 ( ) INSTALL BATH FLOOR COVERING, IF NOT CERAMIC AND DONE EARLIER
- 40 ( ) HARDWARE ON SITE FOR: BATHS, INTERIOR DOORS, CLOSET RODS, DOOR STOPS
- 41 ( ) INSTALL SPECIAL FLOORS: WOOD, VINYL AND CERAMIC
- 41 ( ) INSTALL BATH HARDWARE
- 41 ( ) INSTALL INTERIOR DOOR HARDWARE
- 41 ( ) INSTALL CLOSET RODS
- 41 ( ) HEATING AND AIR CONDITIONING FINAL INSTALLATION
- 41 ( ) INSTALL MEDICINE CABINETS AND/OR MIRRORS
- 41 ( ) LIGHTING FIXTURES AND BULBS ON SITE
- 42 ( ) ELECTRICAL FINAL: INSTALL LIGHTING FIXTURES AND SWITCH PLATES
- 42 ( ) SET COMMODES
- 43 ( ) GET PERMANENT ELECTRICAL POWER
- 43 ( ) INSTALL CARPETING
- 43 ( ) COMPLETE ALL CONCRETE
- 44 ( ) LANDSCAPE
- 45 ( ) CLEAN UP HOUSE AND LOT
- 46 ( ) SET SPLASH BLOCKS
- ENJOY YOUR BEAUTIFUL NEW HOME, Michael Herold - Sculptor